Newmans Timeline

COFFIN WORKS TIMELINE

Date

Activity

2000

English Heritage surveyed Jewellery Quarter and identified Newman Brothers Coffin Works as one of the most important survivals in the Quarter

Building photographed

Dec 2000

Niall Phillips Architects commissioned to undertake a feasibility study by Birmingham City Council, part funded by National Trust

2001

Jan 2001 onwards

Miss Green winding down the business

April 2001

Feasibility study completed which identifies Birmingham Conservation Trust as ideal vehicle to undertake the project

July 2001

English Heritage monograph on the building published

Dec 2001

BCT secures loan from Architectural Heritage Fund to purchase factory

2002

Jan – Nov 2002

BCT doing business planning/ research

Nov 2002

Outline bid submitted to AWM

2003

March 2003

AWM buy the building and contents on understanding BCT will undertake the project

August 2003

Coffin Works on first BBC Restoration programme

September 2003

Record visitor numbers at the Factory Heritage Open Day openings

2004

Feb 2004

Uncertainty over funding stalls project until April 05

July 2004

Lucinda Lampton features Newman Brothers on Hidden Treasurers Radio 4, 30 min programme

2005

May – Nov 2005

Contamination testing and further project development

2006

Jan – Aug 2006

Full business plan developed, plus architectural options

Sept 2006

Full bid submitted to Zone board and approval secures for £1.5m funding

October 2006

Filming of former owner and workers memories

Dec 2006

AWM decided to only accept the bid as outline one with development funding.  Outline approval secured for £198,558 development funding and £1.5 total funding

Dec 2006

BBC Inside Out do feature on Newman Brothers with Julian Litten

2007

Jan 2007

Start monthly meetings with AWM

Feb 2007

Measured survey completed

Feb – June 2007

Full professional team appointed

June – Sept 2007

Cataloguing of contents and removal to secure store

Sept 2007

HLF Project planning grant secured

Dec 2007

Designs submitted to Access Committee

2008

June 2008

Planning permission and Listed Building consent applied for

July 2008

Access and Audience Development Plans completed

September 2008

Planning permissions secured and HLF stage one bid submitted

December 2008

Interpretation plan completed

Operator for museum areas established

December 2008

HLF bid for £1m turned down, suggest re-submitting for £500,000

2009

March 2009

HLF bid re-submitted

March 2009

Full application to AWM ready for submission

April 2009

AWM inform us that they have had funding cut

July 2009

AWM inform us that they are withdrawing funding for the project