COFFIN WORKS TIMELINE
|
Date |
Activity |
|
2000 |
|
|
|
English Heritage surveyed Jewellery Quarter and identified Newman Brothers Coffin Works as one of the most important survivals in the Quarter Building photographed |
|
Dec 2000 |
Niall Phillips Architects commissioned to undertake a feasibility study by Birmingham City Council, part funded by National Trust |
|
2001 |
|
|
Jan 2001 onwards |
Miss Green winding down the business |
|
April 2001 |
Feasibility study completed which identifies Birmingham Conservation Trust as ideal vehicle to undertake the project |
|
July 2001 |
English Heritage monograph on the building published |
Dec 2001 |
BCT secures loan from Architectural Heritage Fund to purchase factory |
2002 |
|
Jan – Nov 2002 |
BCT doing business planning/ research |
|
Nov 2002 |
Outline bid submitted to AWM |
2003 |
|
March 2003 |
AWM buy the building and contents on understanding BCT will undertake the project |
August 2003 |
Coffin Works on first BBC Restoration programme |
|
September 2003 |
Record visitor numbers at the Factory Heritage Open Day openings |
|
2004 |
|
|
Feb 2004 |
Uncertainty over funding stalls project until April 05 |
|
July 2004 |
Lucinda Lampton features Newman Brothers on Hidden Treasurers Radio 4, 30 min programme |
2005 |
|
May – Nov 2005 |
Contamination testing and further project development |
|
2006 |
|
|
Jan – Aug 2006 |
Full business plan developed, plus architectural options |
|
Sept 2006 |
Full bid submitted to Zone board and approval secures for £1.5m funding |
|
October 2006 |
Filming of former owner and workers memories |
|
Dec 2006 |
AWM decided to only accept the bid as outline one with development funding. Outline approval secured for £198,558 development funding and £1.5 total funding |
|
Dec 2006 |
BBC Inside Out do feature on Newman Brothers with Julian Litten |
|
2007 |
|
|
Jan 2007 |
Start monthly meetings with AWM |
|
Feb 2007 |
Measured survey completed |
|
Feb – June 2007 |
Full professional team appointed |
|
June – Sept 2007 |
Cataloguing of contents and removal to secure store |
|
Sept 2007 |
HLF Project planning grant secured |
|
Dec 2007 |
Designs submitted to Access Committee |
|
2008 |
|
|
June 2008 |
Planning permission and Listed Building consent applied for |
|
July 2008 |
Access and Audience Development Plans completed |
|
September 2008 |
Planning permissions secured and HLF stage one bid submitted |
|
December 2008 |
Interpretation plan completed Operator for museum areas established |
|
December 2008 |
HLF bid for £1m turned down, suggest re-submitting for £500,000 |
|
2009 |
|
|
March 2009 |
HLF bid re-submitted |
|
March 2009 |
Full application to AWM ready for submission |
|
April 2009 |
AWM inform us that they have had funding cut |
|
July 2009 |
AWM inform us that they are withdrawing funding for the project |